    I tackled my first handrail job just before Thanksgiving last year. I wish I would have taken more pictures, but this is all I have. I learned a ton and I can't wait till my next set.
    Attached Files

  • #2
    That looks really nice - good job!


    • #3
      Nice work, I really like the beefy look and the large head bolts or lags which ever they may be.

      Miller 211 A.S. and Spoolmate 100
      Stickmate LX 235 AC / 160 DC.
      Clarke 180 EN Just in case
      Spectrum 375 X-Treme.
      O/A Medium Radnor Torch, Large Victor Torch.
      Milwaukee 14" Chop Saw.
      4 x 6 Horizontal Band Saw.
      Rockworth 80 Gallon 2 Stage 16 SCFM @ 175 PSI , 15 SCFM @ 90 PSI.
      Jackson Passive shade #5 for the plasma.
      I almost forgot the Hobart XVP AD Hood.

      Projects and Misc Albums Feel Free to Have a Look ( Just keep in mind I am an amateur )


      • #4
        looks really sturdy


        • #5
          Great Work! I agree about the fasteners, good job with the scale.

          Trying to succeed, Learning by failing
          HH210 (Merry Christmas to Me)
          HH 140
          Hyper Therm Powermax 600
          Hobart Stickmate AC/DC
          Victor & Harris Oxy/Act
          HydMech 225 cold saw
          several grinders
          Rigid Chop Saw
          4x6 band saw
          Never enough clamps


          • #6
            Did you fab it all in place or make sections elsewhere & then install them on site?
            Trailblazer 250g
            22a feeder
            Lincoln ac/dc 225
            Victor O/A
            MM200 black face
            Whitney 30 ton hydraulic punch
            Lown 1/8x 36" power roller
            Arco roto-phase model M
            Vectrax 7x12 band saw
            Miller spectrum 875
            30a spoolgun w/wc-24
            Syncrowave 250


            • #7
              Thanks, I made the pieces on the flats in my shop, and went ahead and pre-cut all my pieces going up the stairs and welded them in place. The home owner wanted to have a industrial look, so I used 10" channel to cover up the stair tread. The rest is 1 1/2" and 3/4" tubing. Can't wait to do another set.


              • #8
                Glad to see someone following current International Residential Code.

                Just some food for thought, though. Not knocking your project at all, but here is a little bit of a pitfall.

                A lot of localities take years and years to adopt the latest editions of IRC and IBC. The 2000 edition of IRC stated in R316.2 that railings "shall not be constructed with horizontal members or other ornamental pattern that results in a ladder effect."

                Because that statement WAS in the building code, anyone that wants horizontal elements in a railing system provides me with a waiver before I cut metal. That way, when some retarded kid climbs over the edge, the lawyers have one more hurdle. A smart lawyer would point out the old code and argue that the design is still an attractive nuisance inherently dangerous to children.

                80% of failures are from 20% of causes
                Never compromise your principles today in the name of furthering them in the future.
                "All I ever wanted was an honest week's pay for an honest day's work." -Sgt. Bilko
                "We are generally better persuaded by reasons we discover ourselves than by those given to us by others." -Pascal
                "Since we cannot know all that there is to be known about anything, we ought to know a little about everything." -Pascal


                • #9
                  well said doubt

                  but that is some great looking work !

                  hem-saws vert. and horiz.
                  cnc 8x14 plas-cutter
                  wysong 10 ft shear
                  wysong 8ft brake
                  100 ton edwards ironworker
                  precision 275
                  synchro 250
                  hypertherm 1650
                  spectrum 875
                  spectrum 2050
                  3 millermatics
                  renegade 180
                  keystone studwelder

                  a pen
                  and a nice chair


                  • #10
                    Good point bagger, I really need to get a copy of all the proper codes. I did contact the local building inspector and he told me as long as obeyed the 4" sphere rule I would be ok, vertical or horizontal. Thanks for the heads up though, good idea about the waiver.


                    • #11
                      The ladder effect portion of the code is left up to alot of interpretation by your inspector. We do lots of rails like this and inspectors dont ever say a word. Last year we had a client who wanted cable rail. She had already had words with the inspector about other things so I knew to talk to him first. He said no horizontal members at all! A month later,a house two houses down has cable rail. Do some research on NOMMA about this dumb code.