You may be able to get by with older equipment, but how much is it costing you?

Team Industries Example

(This example only focuses on the three specific items that Team Industries identified as high replacement items in old welding equipment.)

FUNCTION PART LABOR TOTAL/
YEAR
Mode Switch 3@$186 ea. + 6hr@$50 per =
$858
Fan Motor 1@$125 ea. + 2hr@$50 per =
$225
PC Board 1@$574 ea. + 1hr@$50 per =
$624
TOTAL (per machine)
$1,707
  x
18 (no. units)
TOTAL TEAM INDUSTRIES'
COST PER YEAR
(18 DC250S)
$30,726

Now it's your turn.
Print out and fill in the blanks.

Estimate your maintenance and repair costs per machine.

FUNCTION PART LABOR TOTAL/
YEAR
     +     
=
 
  +  
=
 
  +  
=
 
TOTAL (per machine)
 
  x
(no. units)
TOTAL COST PER YEAR
$